Current Projects

Berkshire & Grevelia Pocket Park

Berkshire & Grevelia Pocket Park 

PROJECT DESCRIPTION

 The City of South Pasadena’s Capital Improvement Program will introduce the development of two new neighborhood pocket parks on vacant parcels to expand access to green space and enhance community recreation.

Berkshire Pocket Park will be built on a 7,482 square foot site and will include a gated, signed entrance, a walking path, a landscaped gathering area with picnic tables and seating, a four-square play court, outdoor fitness equipment, and an open turf play area. The park will feature new trees and landscaping, benches, lighted bollards, a drinking fountain, a pet waste station, and trash and recycling receptacles.

Grevelia Pocket Park will be developed on a 9,130 square foot site with access from Grevelia Street. The park will feature a signed, lighted entrance, a circular plaza with a rock and succulent garden and public art, seating and tables, a walking path, children’s play equipment, a passive turf play area, and a circular seating area around a tree. Additional amenities include landscaping, new trees, benches, lighted bollards, a drinking fountain, a pet waste station, and trash and recycling receptacles. 

 

TIMELINE

Grand opening scheduled for December 17, 2025.

 

QUESTIONS? For any questions related to the project, please reach out to Project Manager Michael Vartanians
mvartanians@southpasadenaca.gov.

 

FY25-26 Street Improvement Project

FY25-26 Street Improvements

PROJECT DESCRIPTION The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Projected start date September 22, 2025.

The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience and support while we work to improve our community.

TIMELINE

Monday - September 29, 2025 Projected Start Date
  • City will commence the project.
September 29, 2025 - January 30, 2026 Water Improvements
  • Water main Line
  • Water Meters

Impacted Streets

Mill Road
(Garfield to End of Street)

October 13, 2025 - December 5, 2025

Edgewood Dr.
(Milan to Wayne)

October 13, 2025 - December 12, 2025

Milan Ave.
(Oak to Edgewood)

November 10, 2025 - December 12, 2025

Oneonta Knoll St.
(Fremont to Primrose)

December 1, 2025 - January 9, 2026

Maple St.
(Fremont to Primrose)

January 5, 2026 - January 23, 2026

Maple St.
(Meridian Ave. to Huntington Drive)

January 12, 2026 - January 29, 2026

Pine St.
(Meridian to Fremont)

January 26, 2026 - February 20, 2026

Glendon Way
(Monterey to Lyndon)

February 9, 2026 - February 27, 2026

Arroyo Verde Rd.

February 23, 2026 - March 20, 2026

October 20, 2025 - March 6, 2026

Concrete Improvements

Impacted Streets

Mill Road
(Garfield to End of Street)

December 1, 2025 - April 3, 2026

Edgewood Dr.
(Milan to Wayne)

December 8, 2025 - December 18, 2025

Milan Ave.
(Oak to Edgewood)

December 8, 2025 - December 18, 2025

Oneonta Knoll St.
(Fremont to Primrose)

January 5, 2026 - January 16, 2026

Maple St.
(Fremont to Primrose)

January 19, 2026 - January 30, 2026

Maple St.
(Meridian Ave. to Huntington Drive)

January 26, 2026 - February 13, 2026

Pine St.
(Meridian to Fremont)

February 9, 2026 - February 27, 2026

Glendon Way
(Monterey to Lyndon)

March 2, 2026 - March 13, 2026

Arroyo Verde Rd.

March 23, 2026 - April 3, 2026

November 10, 2025 - March 20, 2026

Asphalt Improvements

Impacted Streets

Mill Road
(Garfield to End of Street)

January 5, 2026 - January 9, 2026

Edgewood Dr.
(Milan to Wayne)

January 5, 2026 - January 9, 2026

Milan Ave.
(Oak to Edgewood)

January 5, 2026 - January 9, 2026

Oneonta Knoll St.
(Fremont to Primrose

March 9, 2026 - March 20, 2026

Maple St.
(Fremont to Primrose)

March 9, 2026 - March 20, 2026

Maple St.
(Meridian Ave. to Huntington Drive)

March 16, 2026 - March 20, 2026

Pine St.
(Meridian to Fremont)

March 16, 2026 - March 20, 2026

Glendon Way
(Monterey to Lyndon)

March 18, 2026 - March 20, 2026

Arroyo Verde Rd.

March 6, 2026 - March 10, 2026

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

PRESENTATION

September 8, 2025 Town Hall Meeting Presentation Link
FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)

 QUESTIONS? For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov.

FY25-26 Street Rehabilitation Project Map.jpg