Current Projects

FY25-26 Street Improvement Project

FY25-26 Street Improvements

PROJECT DESCRIPTION The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Projected start date September 22, 2025.

The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience and support while we work to improve our community.

TIMELINE

Monday - September 29, 2025 Projected Start Date
  • City will commence the project.
September 2025 - April 2026 Water Improvements
  • Water main Line
  • Water Meters

Impacted Streets

Edgewood Drive October 13, 2025 - February 13, 2026
Milan Avenue November 10, 2025 - February 20, 2026
Oneonta Knoll St November 10, 2025 - February 20, 2026
Maple Street (East) January 12, 2026 - February 20, 2026
Pine Street February 9, 2026 - March 13, 2026
Maple Street (West) March 2, 2026 - March 27, 2026
Glendon Way March 9, 2026 - April 3, 2026
Arroyo Verde Road March 23, 2026 - April 17, 2026
December 2025 - May 2026

Concrete Improvements

Impacted Streets

Edgewood Drive February 9, 2026 - February 13, 2026
Milan Avenue February 12, 2026 - February 20, 20226
Oneonta Knoll Street February 23, 2026 - March 6, 2026
Maple Street (East) March 9, 2026 - March 20, 2026
Pine Street March 23, 2026 - April 10, 2026
Maple Street (West) March 27, 2026 - April 16, 2026
Glendon Way April 6, 2026 - April 17, 2026
Arroyo Verde Road April 20, 2026 - May 1, 2026
January 2026 - May 2026

Asphalt Improvements

Impacted Streets

Mill Road February 23, 2026 - February 27, 2026
Edgewood Drive February 23, 2026 - February 27, 2026
Milan Avenue February 23, 2026 - February 27, 2026
Oneonta Knoll Street April 27, 2026 - May 8, 2026
Maple Street (East) April 27, 2026 - May 8, 2026
Maple Street (West) May 4, 2026 - May 8, 2026
Pine Street May 4, 2026 - May 8, 2026
Glendon Way May 6, 2026 - May 8, 2026
Arroyo Verde Road May 11, 2026 - May 15, 2026

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

PRESENTATION

September 8, 2025 Town Hall Meeting Presentation Link
FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)

 QUESTIONS? For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov.

FY25-26 Street Rehabilitation Project Map.jpg