FY25-26 Street Improvements
The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026.
The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community
Click here to view the latest progress update! (PDF, 190KB)
Water Improvements - Sept. 2025 - May 2026
Water Improvements
- Water main Line
- Water Meters
Impacted Streets
| Edgewood Drive |
October 13, 2025 - March 4, 2026 |
| Milan Avenue |
November 10, 2025 - March 12, 2026 |
| Maple Street (East) |
January 12, 2026 - April 2, 2026 |
| Oneonta Knoll Street |
December 4, 2025 - April 16, 2026 |
| Pine Street |
February 18 2026 - May 14, 2026 |
| Maple Street (West) |
March 23, 2026 - April 21, 2026 |
| Glendon Way |
April 6, 2026 - May 1, 2026 |
| Arroyo Verde Road |
March 23, 2026 - May 12, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Concrete Improvements - Dec. 2025 - June2026
Impacted Streets
| Mill Road |
December 1, 2025 - April 3, 2026 |
| Edgewood Drive |
March 2, 2026 - March 20, 2026 |
| Milan Avenue |
March 16, 2026 - April 3, 2026 |
| Maple Street (East) |
April 6, 2026 - April 17, 2026 |
| Oneonta Knoll Street |
April 13, 2026 - April 17, 2026 |
| Pine Street |
April 20, 2026 - May 15, 2026 |
| Maple Street (West) |
May 11, 2026 - May 29, 2026 |
| Glendon Way |
June 1, 2026 - June 12, 2026 |
| Arroyo Verde Road |
June 15, 2026 - June 19, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Asphalt Improvements - Jan. 2026 - May 2026
Impacted Streets
| Mill Road |
April 6, 2026 - April 10, 2026 |
| Edgewood Drive |
April 6, 2026 - April 10, 2026 |
| Milan Avenue |
April 6, 2026 - April 10, 2026 |
| Oneonta Knoll Street |
June 15, 2026 - June 19, 2026 |
| Maple Street (East) |
June 15, 2026 - June 19, 2026 |
| Maple Street (West) |
June 15, 2026 - June 19, 2026 |
| Pine Street |
June 22, 2026 - June 26, 2026 |
| Glendon Way |
June 22, 2026 - June 23, 2026 |
| Arroyo Verde Road |
June 22, 2026 - June 26, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Presentation
September 8, 2025 Town Hall Meeting Presentation Link
FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)
Questions
For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov