FY25-26 Street Improvements
The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026.
The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community
Click here to view the latest progress update!(PDF, 140KB)
Water Improvements - Sept. 2025 - May 2026
Water Improvements
- Water Main Line
- Water Meters
Impacted Streets
| Mill Road |
March 2, 2026 - April 3, 2026 |
| Edgewood Drive |
March 4, 2026 - April 23, 2026 |
| Milan Avenue |
March 26, 2026 - March 26, 2026 |
| Maple Street (East) |
March 19, 2026 - April 1, 2026 |
| Oneonta Knoll Street |
April 6, 2026 - April 16, 2026 |
| Pine Street |
February 18, 2026 - April 24, 2026 |
| Maple Street (West) |
March 23, 2026 - April 17, 2026 |
| Glendon Way |
March 30, 2026 - April 24, 2026 |
| Arroyo Verde Road |
April 1, 2026 - April 24, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Concrete Improvements - Dec. 2025 - June2026
Impacted Streets
| Mill Road |
March 5, 2026 - March 27, 2026 |
| Edgewood Drive |
March 2, 2026 - March 27, 2026 |
| Milan Avenue |
March 9, 2026 - March 27, 2026 |
| Maple Street (East) |
March 30, 2026 - April 10, 2026 |
| Oneonta Knoll Street |
April 6, 2026 - April 10, 2026 |
| Pine Street |
April 13, 2026 - May 1, 2026 |
| Maple Street (West) |
April 20, 2026 - May 8, 2026 |
| Glendon Way |
May 11, 2026 - May 22, 2026 |
| Arroyo Verde Road |
May 18, 2026 - May 22, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Asphalt Improvements - Jan. 2026 - May 2026
Impacted Streets
| Mill Road |
April 6, 2026 - April 10, 2026 |
| Edgewood Drive |
April 6, 2026 - April 10, 2026 |
| Milan Avenue |
April 6, 2026 - April 10, 2026 |
| Oneonta Knoll Street |
May 11, 2026 - May 15, 2026 |
| Maple Street (East) |
May 11, 2026 - May 15, 2026 |
| Pine Street |
May 18, 2026 - May 22, 2026 |
| Maple Street (West) |
May 18, 2026 - May 22, 2026 |
| Glendon Way |
May 25, 2026 - May 29, 2026 |
| Arroyo Verde Road |
May 25, 2026 - May 29, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Presentation
September 8, 2025 Town Hall Meeting Presentation Link
FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)
Questions
For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov