FY25-26 Street Improvements

The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026. 

The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community

Click here to view the latest progress update!(PDF, 143KB)

Water Improvements - Sept. 2025 - May 2026

Water Improvements

  • Water Main Line
  • Water Meters

Impacted Streets

Oneonta Knoll Street May 21, 2026 - June 11, 2026
Pine Street May 28, 2026 - July 14, 2026
Maple Street (West) April 23, 2026 - June 25, 2026
Glendon Way May 12, 2026 - June 19, 2026
Arroyo Verde Road (Pending METRO) June 1, 2026 - September 4, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

Concrete Improvements - Dec. 2025 - June2026

Impacted Streets

Milan Avenue March 9, 2026 - June 19, 2026
Maple Street (East) April 20, 2026 - May 22, 2026
Oneonta Knoll Street April 20, 2026 - June 5, 2026
Maple Street (West) June 22, 2026 - July 3, 2026
Pine Street July 20, 2026 - July 31, 2026
Glendon Way June 29, 2026 - July 10, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

Asphalt Improvements - Jan. 2026 - May 2026

Impacted Streets

Milan Avenue (On Hold Trees) June 22, 2026 - June 26, 2026
Maple Street (East) June 29, 2026 - July 3, 2026
Oneonta Knoll Street June 29, 2026 - July 3, 2026
Maple Street (West) July 6, 2026 - July 10, 2026
Pine Street August 3, 2026 - August 7, 2026
Glendon Way July 13, 2026 - July 17, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

 

Presentation

September 8, 2025 Town Hall Meeting Presentation Link

FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)

Questions

For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov

FY25-26 Street Rehabilitation Project Map.jpg