FY25-26 Street Improvements

The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026. 

The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community

Click here to view the latest progress update!(PDF, 140KB)

Water Improvements - Sept. 2025 - May 2026

Water Improvements

  • Water Main Line
  • Water Meters

Impacted Streets

 Mill Road March 2, 2026 - April 3, 2026
Edgewood Drive March 4, 2026 - April 23, 2026
Milan Avenue March 26, 2026 - March 26, 2026
Maple Street (East) March 19, 2026 - April 1, 2026
Oneonta Knoll Street April 6, 2026 - April 16, 2026
Pine Street February 18, 2026 - April 24, 2026
Maple Street (West) March 23, 2026 - April 17, 2026
Glendon Way March 30, 2026 - April 24, 2026
 Arroyo Verde Road April 1, 2026 - April 24, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

Concrete Improvements - Dec. 2025 - June2026

Impacted Streets

Mill Road March 5, 2026 - March 27, 2026
Edgewood Drive March 2, 2026 - March 27, 2026
Milan Avenue March 9, 2026 - March 27, 2026
Maple Street (East) March 30, 2026 - April 10, 2026
Oneonta Knoll Street April 6, 2026 - April 10, 2026
Pine Street April 13, 2026 - May 1, 2026
Maple Street (West) April 20, 2026 - May 8, 2026
Glendon Way May 11, 2026 - May 22, 2026
Arroyo Verde Road May 18, 2026 - May 22, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

Asphalt Improvements - Jan. 2026 - May 2026

Impacted Streets

Mill Road April 6, 2026 - April 10, 2026
Edgewood Drive April 6, 2026 - April 10, 2026
Milan Avenue April 6, 2026 - April 10, 2026
Oneonta Knoll Street May 11, 2026 - May 15, 2026
Maple Street (East) May 11, 2026 - May 15, 2026
Pine Street May 18, 2026 - May 22, 2026
Maple Street (West) May 18, 2026 - May 22, 2026
Glendon Way May 25, 2026 - May 29, 2026
Arroyo Verde Road May 25, 2026 - May 29, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

 

Presentation

September 8, 2025 Town Hall Meeting Presentation Link

FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)

Questions

For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov

FY25-26 Street Rehabilitation Project Map.jpg