FY25-26 Street Improvements
The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026.
The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community
Click here to view the latest progress update!(PDF, 144KB)
Progress Updates
- Progress Update - April 23, 2026(PDF, 144KB)
- Progress Update - April 8, 2026(PDF, 142KB)
- Progress Update - March 26, 2026(PDF, 141KB)
- Progress Update - March 12, 2026(PDF, 140KB)
- Progress Update - February 26, 2026(PDF, 190KB)
Water Improvements - Sept. 2025 - May 2026
Water Improvements
- Water Main Line
- Water Meters
Impacted Streets
| Pine Street |
April 20, 2026 - May 29, 2026 |
| Maple Street (West) |
April 23, 2026 - May 29, 2026 |
| Glendon Way |
May 4, 2026 - May 22, 2026 |
| Arroyo Verde Road |
May 7, 2026 - May 29, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Concrete Improvements - Dec. 2025 - June2026
Impacted Streets
| Edgewood Dr. |
March 2, 2026 - April 24, 2026 |
| Milan Ave. |
March 9, 2026 - April 24, 2026 |
| Maple Street (East) |
April 20, 2026 - May 1, 2026 |
| Oneonta Knoll Street |
April 20, 2026 - May 1, 2026 |
| Pine Street |
May 4, 2026 - May 15, 2026 |
| Maple Street (West) |
May 11, 2026 - May 29, 2026 |
| Glendon Way |
May 18, 2026 - May 29, 2026 |
| Arroyo Verde Road |
May 25, 2026 - May 29, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Asphalt Improvements - Jan. 2026 - May 2026
Impacted Streets
| Mill Road |
April 22, 2026 - April 27, 2026 |
| Edgewood Dr. |
April 22, 2026 - April 27, 2026 |
| Milan Ave (On Hold Trees) |
April 27, 2026 - May 15, 2026 |
| Oneonta Knoll Street |
May 4, 2026 - May 8, 2026 |
| Maple Street (East) |
May 4, 2026 - May 8, 2026 |
| Pine Street |
May 18, 2026 - May 22, 2026 |
| Maple Street (West) |
June 1, 2026 - June 5, 2026 |
| Glendon Way |
June 1, 2026 - June 5, 2026 |
| Arroyo Verde Road |
June 1, 2026 - June 5, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Presentation
September 8, 2025 Town Hall Meeting Presentation Link
FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)
Questions
For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov