FY25-26 Street Improvements

The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026. 

The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community

Click here to view the latest progress update!(PDF, 142KB)

Water Improvements

 Water Improvements

  • Water Main Line
  • Water Meters

Impacted Streets

Arroyo Verde Road (Pending METRO) October 6, 2026 - November 13, 2026
 Sycamore Avenue (Tentative) September 4, 2026 - October 27, 2026

 

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

Concrete Improvements

Impacted Streets

Pine Street August 10, 2026 - November 13, 2026
Glendon Way October 19, 2026 - November 13, 2026

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

Asphalt Improvements

Impacted Streets

 Maple Street July 20, 2026 - October 30, 2026 
Pine Street August 6, 2026 - November 20, 2026
Glendon Way October 22, 2026 - November 20, 2026

**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**

 

Presentation

September 8, 2025 Town Hall Meeting Presentation Link

FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)

Questions

For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov

FY25-26 Street Rehabilitation Project Map.jpg