FY25-26 Street Improvements
The FY25-26 (formerly FY19-20) Street Improvement Project will deliver pavement rehabilitation, water and sewer line upgrades, and sidewalk and curb repairs on multiple streets. Construction began in September 2025 and is expected to be completed in summer 2026.
The City of South Pasadena and Gentry Brothers, Inc. thank you for your cooperation, patience, and support while we work to improve our community
Click here to view the latest progress update!(PDF, 143KB)
Progress Updates
- Progress Update - June 4, 2026(PDF, 143KB)
- Progress Update - May 21, 2026(PDF, 144KB)
- Progress Update - May 7, 2026(PDF, 117KB)
- Progress Update - April 23, 2026(PDF, 144KB)
- Progress Update - April 8, 2026(PDF, 142KB)
- Progress Update - March 26, 2026(PDF, 141KB)
- Progress Update - March 12, 2026(PDF, 140KB)
- Progress Update - February 26, 2026(PDF, 190KB)
Water Improvements - Sept. 2025 - May 2026
Water Improvements
- Water Main Line
- Water Meters
Impacted Streets
| Oneonta Knoll Street |
May 21, 2026 - June 11, 2026 |
| Pine Street |
May 28, 2026 - July 14, 2026 |
| Maple Street (West) |
April 23, 2026 - June 25, 2026 |
| Glendon Way |
May 12, 2026 - June 19, 2026 |
| Arroyo Verde Road (Pending METRO) |
June 1, 2026 - September 4, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Concrete Improvements - Dec. 2025 - June2026
Impacted Streets
| Milan Avenue |
March 9, 2026 - June 19, 2026 |
| Maple Street (East) |
April 20, 2026 - May 22, 2026 |
| Oneonta Knoll Street |
April 20, 2026 - June 5, 2026 |
| Maple Street (West) |
June 22, 2026 - July 3, 2026 |
| Pine Street |
July 20, 2026 - July 31, 2026 |
| Glendon Way |
June 29, 2026 - July 10, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Asphalt Improvements - Jan. 2026 - May 2026
Impacted Streets
| Milan Avenue (On Hold Trees) |
June 22, 2026 - June 26, 2026 |
| Maple Street (East) |
June 29, 2026 - July 3, 2026 |
| Oneonta Knoll Street |
June 29, 2026 - July 3, 2026 |
| Maple Street (West) |
July 6, 2026 - July 10, 2026 |
| Pine Street |
August 3, 2026 - August 7, 2026 |
| Glendon Way |
July 13, 2026 - July 17, 2026 |
**Schedules are subject to change due to weather conditions or other unforeseen factors. If construction work does not occur on the posted date, the work will be rescheduled, and new signs will be posted.**
Presentation
September 8, 2025 Town Hall Meeting Presentation Link
FY-25-26-Street-Improvement-Project-Presentation.pdf(PDF, 2MB)
Questions
For any questions related to the project, please reach out to Project Manager Michael Vartanians mvartanians@southpasadenaca.gov